Warwick Road Update

The work to open Station Road up to two way traffic has been completed. This is an experimental change, so we'll need to keep a close eye on it. BT also completed work to redirect some of their utilities around Victoria Road.

The pictures also show the removal of the trees from the central reservation. Work has also been done to remove the furniture from the central reservation and will continue this week. Some of the blocks used to make up the retaining wall on the reservation originally formed part of the wall of the convent. These have been saved for reuse as part of the scheme.

Some pedestrian crossing points may need to be adjusted, but safe crossing points will be maintained.

The contractors are required to keep one lane running in each direction, but there may be the occasional need for traffic control, as there was last week with the tree felling.